Roraback Pond Dam
Project Highlights
Location: Harwinton, CT
Year Completed: 1996
Cost: $1.1 M
REFERENCE: Ted Rybak Dept Of Environmental Protection Inland Water Resources Division
79 Elm Street Hartford, CT 06106-5127
PRINCIPAL: James Brockman, P.E.
PROJECT MANAGER: John Brochu, P.E.
WATERSHED AREA: 10.4 Square Miles
LAKE AREA: 12.7 Acres
DESCRIPTION: The reconstruction of the Roraback Pond Dam consisted of the complete reconstruction of the earthen dam incorporating a concrete cutoff wall. An overflow spillway and a new drawdown chamber were also added. Interesting features of this project included the installation of a diversion structure from Leadmine Brook to Roraback Pond. Also, two overflow ponds were created downstream from the spillway to provide new wetland habitat for both flora and fauna.
Macchi Engineers' responsibilities included full-time, on-site construction administration and inspection.