Project Highlights

Location: Litchfield, CT
Year Completed: 2004
Cost: $405,000

PRINCIPAL-IN-CHARGE: James Brockman, P.E., 860/549-6190, X101
PROJECT MANAGER: John Brochu, P.E., 860/549-6190, X112 
REFERENCE: Art Christian DEP, IWRD 79 Elm Street Hartford, CT 06106-5127 860/424-3880
WATERSHED AREA: 2.35 square miles 
LAKE AREA: 20.2 Acres 

DESCRIPTION: The Northfield Pond Dam project consisted of a Phase II Study to document the current condition of the dam and determine possible repairs. Our study entailed a thorough field investigation that included the use of certified divers, a topographic survey, and a complete hydrologic and hydraulic analysis.


The final design for the repairs included the construction of a new upstream wall to improve stability and reduce seepage as well as design of a new drawdown chamber, slope protection, and toe drain.

Macchi Engineers was also responsible for the construction administration, construction inspection, shop drawing review and the development of As-Built Drawings for the repairs to the Northfield Pond Dam.

Project Categories

 

Testimonials

We place a great deal of value in what our clients say about working with us. More

Our Awards

While our favorite recognition is meeting and exceeding our clients expectations, it's nice to win an award or two now and then! More