Eastern Connecticut State University Perimeter Road
Project Highlights
Location: Willimantic, CT
Year Completed: 2001
Cost: $920,000
REFERENCE: State of Connecticut Department of Public Works
165 Capitol Avenue, Hartford, CT 06106
PRINCIPAL-IN-CHARGE: James Brockman, P.E., 860/549-6190, X101
PROJECT DURATION: May 1997 – 2000
TOTAL LENGTH: 0.53 miles
PARKING SPACES: 362
DESCRIPTION: Macchi Engineers provided the civil design services for the complete reconstruction of the main campus drive at Eastern Connecticut State University including a new storm drainage system, utility coordination and roadway lighting. Additional site elements included the construction of two large parking areas and the reconstruction of two intersections. In addition, a storm drainage master plan for the entire campus was developed and included a detention basin designed to control the increase in runoff and reduce sedimentation of the nearby wetlands.